ME472 - Spring 2007 Calendar (Final Version, updated 6/4/07)
|
|||||
|
Tuesday (11-12) |
|
Thursday (11-12) |
|
Friday (11-1) |
|
|
April |
27
ME472
Info Sheet (pdf) Vote for ME Department's outstanding
senior leader Discuss Customer
Demo Day: |
|
29 11:35 Team 2 meeting Teams not in
project/status meetings do mfg work (report to lab or record your mfg related
activity in your notebook) |
|
30 11:35 Team 3 mtg in 192 12:05 Team 4 mtg in 103 12:30 Team 6 mtg in 103
|
|
3 ASME
Student Project Competition 2007 >For design projects presented through a project website by Ugrads who are ASME members >Approved projects will
be linked to the ASME website >4 projects will be
selected for presentation at a conference in Las Vegas, with a minimum award
of $500 ($1000 for the winner) and a travel allowance of $500. Liebert Project Documentation Table Example
Analysis Report from Industry > Shows good FBDs and level of detail for discussion of analysis Updated
SrD Design Report 07 guidelines >Sections 7&8 of Report >Drawings & parts
lists >Production Plans >Appendices Review Manufacturing
Cost Issues – (ME board member Suzanne Tkach) Cost
Estimation Method Recommended for Sr Design Suggested Project Milestone: Mockup work complete. Prototype construction fully planned /
scheduled. Significant prototype
construction begun. |
|
5 (focused more on details
of design and analysis for a subsystem) or > Hocking River Pirates > Athens County Choppers All members of the
presenting teams and at least 3 appropriate representatives from the other
teams should attend. Those not
attending must spend the time in prototype mfg activities. |
|
6 (in room 103) Final Design - Mini
Design Review presentation (focused more on details
of design and analysis for a subsystem) or > Sembilanagon > MeCat > Sunken Boat All members of the presenting
teams and at least 3 appropriate representatives from the other teams should
attend. Those not attending must spend
the time in prototype mfg activities. |
|
|
10 11:10 Team 4 meeting 11:35 Team 3 meeting Reps from teams 1, 2, and
5 must meet with Scott in 011 to plan the demo day. Suggested Project Milestone: Major subsystems construction 1/3 complete |
|
12 11:10 Team 2 meeting 11:35 Team 5 meeting Reps from teams 3, 4, and
6 must meet with Scott in 011 to plan the demo day. |
|
13 All teams do mfg work Project Milestone: All prototype purchases completed. |
|
|
17 > Sunken Boat > MeCat All members of the
presenting teams and at least 3 appropriate representatives from the other
teams should attend. Those not
attending must spend the time in prototype mfg activities. Suggested Project Milestone: Major subsystems construction 2/3 complete. |
|
19 > Sembilanagon >Goonies All members of the
presenting teams and at least 3 appropriate representatives from the other
teams should attend. Those not
attending must spend the time in prototype mfg activities. |
|
20 11:10 Team 1 meeting (192) 11:35 Team 6 meeting (192) 12-1 LT
Review - Presentation (103) > Athens County
Choppers > Hocking River Pirates All members of the presenting teams and at least 3 appropriate representatives from the other teams should attend. Those not attending must spend the time in prototype mfg activities. |
|
|
24 11:10 Team 6 meeting 11:35 Team 1 meeting Other teams - prototype
work Suggested Project Milestone: Major subsystems construction complete. System integration underway. |
|
26 11:10 Team 3 meeting 11:35 Team 4 meeting Other teams - prototype
work |
|
27 Team meetings - please
bring current copies of assembly and part drawings for review, with emphasis
on dimensioning and tolerancing. Also, if complete bring outlines or drafts
of the "How it is made" section of the report. 11:10 Team 2 meeting (In
192) 11:35 Team 5 meeting (In
192) Other teams - prototype
work |
|
May
|
1 >Goonies > Sembilanagon > MeCat The entire class is
expected to attend these presentations Suggested Project Milestone: System integration complete. System debugging and "optimization"
underway. |
|
3 Prototype
Review Presentations > Sunken Boat > Hocking River Pirates > Athens County
Choppers The entire class is
expected to attend these presentations
|
|
4 No class - Prepare for the |
|
8 Prototype Work and |
|
10 Prototype Work, and last
chance to pass the |
|
11 10:35 The Goonies 11:00 Board meets with Dean Irwin (108) 11:20 Sunken Boat 11:45 Sembilanagon 12:10 Athens County
Choppers 12:35 Hocking River
Pirates The purpose is two-way
interaction. c) Team members will then
have the opportunity to provide feedback to the board members about the
overall ME program and how they think it prepared them (or failed to) to
start their intended career. >>>Sat May 12, 10 AM
- |
|
|
15 > Please share any good
pictures (action shots and shots of team members working on the projects) and
video Another prototype NEV
Example: The
Solar Bug Plans for rest of quarter: > Schedule review > Report due date
concerns? >
Peer ratings (method to use),
include the development skill? > Awards? > Prototype Display? > Clean up day? > Job info - how best
to share with students > Ideas to make final
day special Library Survey - contact
Andrew at stuarta@ohio.edu for loginID and
password. Extra credit will be given
for participation. |
|
17 11:10 Team 2 meeting 11:35 Team 5 meeting Outlines Due in the mtg for Executive
Summaries and all remaining design report sections |
|
18 11:10 Team 6 meeting 11:35 Team 4 meeting 12:10 Team 1 meeting 12:35 Team 3 meeting Outlines Due in the mtg for Executive
Summaries and all remaining design report sections |
|
|
22 Monday - Peer review preliminary ratings due
by Monday for discussion with teams during class > Complete on
Blackboard > Individual and/or
team PR mtgs will be set as needed based on issues
with ratings Professional
skills draft reflection reports due by end of the day (Tuesday) > Discuss expectations Draft Final
Design Report and draft Executive
Summaries Due by the end of the day Wednesday May 23 > send via Blackboard
Digital Dropbox --------------------------------------- Student Academic Honesty Council survey - In class - to get feedback on the statement of
student responsibilities > Discussion Student Vote: > Best design (combination of being the most marketable product and
having the most positive impact on society, especially related to energy and
the environment) > Best prototype (includes professional look, performance, and
being representative of final design) >Best design team (demonstrated good process throughout) > Most creative and unique design feature. Advisory
Board Feedback for Design teams (Tom Moehring) |
|
24 > Hocking River Pirates > MeCat
The entire class is
expected to attend these presentations Prototype Display (for judging) |
|
25 Final
Design Presentation - Pre-production review >Goonies > Sembilanagon > > Sunken Boat The entire class is
expected to attend these presentations |
|
|
|
29 Quick feedback on
presentations and reports SAB "focus
group" - gather student feedback > Evidence
of Dept. Responses to student feedback Submit Design
Notebooks for final review in class today or in Dr. Kremer's office by noon
Wednesday |
|
31 No class Final
Design Report due before class on Friday > as much as practical
electronically, but some sections can be in hard copy > Submit electronic items
via Blackboard Digital Dropbox > Meet with Dr Kremer
only if there are special considerations to discuss |
|
June 1 Return to 103 for free food and drinks "To
Do" Engineering and "To Be" an Engineer ***Student
feedback (pdf) *** Impact
on plans for next year > Gather job/career
info from all students |
|
|
Final versions of the Peer Ratings must be entered on
Blackboard by Monday June 4 > No action is required
unless you want to change your preliminary rating from May 21 Executive
Summary final copies due by exam
time (but earlier is better) > preferred mode is to submit electronic
copies on the digital drop box on Blackboard Professional
skills reflection report final copies due by exam time (but earlier is
better) > preferred mode is to
submit electronic copies on the digital drop box on Blackboard Final discussions with
teams concerning grades and fulfilling all requirements for SrD (during final
exam time or by appointment at an earlier time) Monday June 4, >
Noon, >
2 PM, Hocking River Pirates, STKR 252 [Copies of HRP
Final Design Report, Appendix,
Design
Project File] Wed Jun 6th > 9:40 AM
Goonies (STKR 252) [Copy
of Goonies Final Design Report] >
10:20 AM Sunken Boat (STKR 103) [Copy
of Sunken Boat Final Design Report] >
10:40 AM Sembilanagon
(STKR 103) [Copy
of Sembilanagon Final Design Report, Drawings] >
11 AM MeCAT
(STKR 103) [Copy
of MeCAT Final Design Report] |
||||
|
|
Resources and
Links Formal
Presentation Rubric (Used for grading/assessing all presentations -
student feedback on the rubric is encouraged) Job Postings (updated ?/?/07) [coming soon] |
||||
Ø
ME470/1/2 Senior Design