Analysis for layout by productLine balancing example cont.
The precedence diagram is:
The target production rate is 160 units per eight-hour shift so the target cycle time is ct = 8 hours ¸ 160 units = 180 seconds (pu)
The (heuristic) rule for assigning tasks to stations is: Choose tasks in descending order of task time